Case and hearings
Key dates
Project timeline
The SCC has established the main case schedule. These milestones show how the community reached this point and what happens next.
Completed milestones
How public participation and the local-hearing request developed- After hearing requests from the Historic Keswick Properties and PEC, the Commission found that case-wide public-witness and evidentiary hearings should be held.
- Albemarle County filed a formal request for a local hearing.
- Residents submitted individual hearing requests in the same SCC case, asking to be heard locally.
- The SCC heard argument on Keswick's request to pause the case during its separate easement lawsuit.
- The stay was denied, and the Hearing Examiner directed that a separate local hearing be scheduled.
- The SCC scheduled public-witness and evidentiary hearings and extended public comments.
- Dominion's deadline passed to mail new notice to affected property owners and publish local newspaper notice.
- Deadline passed to file as a formal respondent in the case. Westminster-Canterbury of the Blue Ridge, the Pantops retirement community, joined as a respondent on September 11, and Dominion filed proof that it mailed and published the new notice.
- The Hearing Examiner ruled on a Keswick discovery dispute: Dominion must supplement its explanation of why it considered no other projects or routes, while questions about the extent of its land rights were left to the circuit court.
- Oral argument in Richmond on a second Keswick discovery motion.
- Hearing Examiner granted part of that motion, directing Dominion to file more cost information.
- Formal parties filed testimony, including Westminster-Canterbury, PEC, and the Keswick landowners.
- Local public hearing held at Charlottesville City Council Chambers.
Upcoming schedule
Key public dates are highlighted- Deadline for residents to register as public witnesses.
- Case-wide telephone public-witness session at 10:00 a.m.
- Extended public-comment deadline.
- Main evidence hearing in the SCC courtroom in Richmond at 10:00 a.m.
- Dominion requested a final SCC order by this date.
- Possible construction start if Dominion's requested schedule holds.
- Dominion's desired completion and in-service target.
Case filings, explained
What's been filed, in plain English.
Most documents in this case are lawyers' paperwork. Here's each recent filing in a sentence or two - and whether it matters to you. Every original is in the SCC case record.
-
RoutineRequest to file one more witness's testimony a day late
Asks permission to add testimony from John D. Carr, manager of the company that owns the land where Castle Hill Cider operates, about the project's effect on that business and the historic landscape. The landowners say it was served on all parties on time but missed the filing deadline.
-
Worth knowingTestimony of visual impact expert Matthew Allen
Says Dominion "failed to perform a site-specific evaluation of visual mitigation measures anywhere along the 15.8-mile project corridor," used only five photo simulations for the whole line, and relied on wide-angle panoramas that make the poles look smaller than they will be.
Supports residents' requests for simulations from where people actually live.
Read the filing -
RoutineTestimony of neighbor Needham Ward
A neighboring landowner on Hansen's Mountain Road supports Westminster-Canterbury's requests: no taller poles if possible, otherwise undergrounding, and if neither, poles moved and lowered where possible.
Read the filing -
Worth knowingTestimony of CFO David Bruton
Westminster-Canterbury, home to more than 450 residents, asks to keep today's pole heights and right-of-way. If the SCC finds an upgrade or expansion necessary, it asks that at least the stretch from the Charlottesville Substation to where Route 250 enters a more rural area go underground.
A formal party asking for targeted undergrounding through Pantops.
Read the filing -
RoutineTestimony of five landowners and additional exhibits
Owners of Castle Hill, East Belmont, Clover Hill, Merifields, and Castalia describe how much taller steel towers would affect historic farms, the Southwest Mountains landscape, and local tourism businesses.
-
Worth knowingTestimony of utility consultant Scott Mallory
Agrees Dominion showed a need to rebuild with a larger single circuit, but says it has not shown a need for the second circuit that drives the taller, double-circuit towers. He also recommends rechecking whether even that single-circuit upgrade is still needed, since other significant transmission upgrades have been approved.
If the second circuit isn't needed now, lower-impact designs become easier to justify.
Read the filing -
Worth knowingTestimony of underground-cable engineer Harry Orton
Says Dominion's undergrounding memo was "not developed as a certifiable project alternative," that its $1.5 billion figure is a screening-level estimate with a stated accuracy of minus 50% to plus 200%, priced in 2030 dollars against a $97 million overhead figure in 2025 dollars, and that burying the line would take about two years of design and permitting plus 12 to 18 months of construction.
Directly disputes Dominion's cost and time reasons for rejecting undergrounding.
Read the filing -
Worth knowingRuling on Keswick's second discovery motion - granted in part
Dominion must file information in its rebuttal testimony on how the project's cost would change if it lacks enough land rights in the existing corridor, and supplement other answers within five business days. The Hearing Examiner noted that Dominion had said it was preparing related cost information, "but no such information has been provided."
More cost numbers should be on the record before the evidentiary hearing.
Read the filing -
RoutineConfidentiality agreements
Standard forms that let their lawyers see documents marked confidential in the case.
-
RoutineOral argument held in Richmond
Lawyers for the Keswick landowners and Dominion argued the second discovery motion. SCC Staff also appeared. The transcript was filed October 15.
-
RoutineResponse opposing Keswick's second discovery motion
Dominion asked the Hearing Examiner to deny the motion as filed too late, or else to uphold its objections to the landowners' questions.
-
RoutineRuling scheduling an October 13 oral argument
The Hearing Examiner will hear oral argument on Keswick's second discovery motion on October 13 at 2 pm in the SCC courtroom in Richmond.
This is argument on a discovery motion, not a public-witness session - residents don't testify here.
-
RoutineRuling setting a response deadline
Gave Dominion until October 8 to respond to the second discovery motion.
-
RoutineSecond discovery motion
Asks Dominion to explain what would happen to the project's cost, schedule, and design if it turns out it lacks enough land rights in the existing corridor - including any contingency plans.
-
Worth knowingRuling on Keswick's discovery motion - granted in part
Dominion must supplement its discovery answer with any additional current reasons, beyond those it has already given, for not considering other projects or routes. Most of Keswick's other requests were denied - including those about the extent of Dominion's land rights, which the Hearing Examiner said is a question for the circuit court, not the SCC.
Keeps the question of alternatives in front of the SCC.
Read the filing -
RoutineReply supporting their discovery motion
The landowners' final argument for why Dominion should have to explain its claim that no new right-of-way is needed anywhere along the corridor.
-
Worth knowingProof that the new notice was mailed and published
Dominion certified that it mailed the July 21 notice and route map to property owners along the corridor and published it in local newspapers.
Didn't get the mailer? You can still take part fully - and it's worth saying so in your public comment.
-
Worth knowingNotice of participation as a formal respondent
The Pantops retirement community, serving more than 470 seniors, joined the case with its own lawyers. Its property borders the corridor, and it says taller lines would affect residents' daily lives and how it can use its land.
Read the filing -
RoutineConfidentiality agreement
A standard form one more Keswick representative signed so he can see documents marked confidential in the case.
-
RoutineResponse opposing Keswick's discovery motion
Dominion argued it had already answered the landowners' questions about its land rights and alternatives, and that searching the whole corridor's records was unnecessary.
-
RoutineRuling setting a fast schedule for Keswick's discovery motion
Gave Dominion until September 9 to respond to the Keswick landowners' request for more documents, and Keswick until September 14 to reply.